Tabletop Pipeline

This project was completed on behalf of the Albury City Council. The project involved the installation of 8km of pipework ranging from 450mm and 300mm DICL pipe, 300mm, 250mm and 200mm PVC pipe. There was multiple HDD bores and sleeved bores using mild steel pipe. Parts of the project were constructed through rock and sensitive vegetation areas.

Jindera Trunk Sewer

We were engaged by The Greater Hume Shire. The project consisted of 1500mts of 150mm and 225mm gravity sewer at depths up to 6mt along with 18 cast in situ manholes. It also included a 200mt rising main. Parts of this project were completed in residents back yards and within road ways.